Bakersfield College

Measure J Project Schedule as of September 8, 2018

2018

  • 8/18/18 – 2/19/18 - Upgrades to wireless Technology on Campus 
  • 9/4/18 – 10/14/18 - P8 (student parking lot on University), P11 (staff parking lot next to LA), Entrance from University closed for renovation
  • 10/8/18 – 10/14/18 – P9 (staff parking lot next to tennis courts) closed for renovation
  • 11/2018 – 11/2019 - Construction of Veterans Resource Center
  • 12/2018 – begin demolition of Campus Center 
  • 12/2018 – Shut down of Kitchen Begins, moved to Huddle 

2019

  • 1/2019 Mt. Vernon and Huddle are operational
  • 12/2019 –7/2019- Construction of Memorial Stadium 
  • 1/2019 - 11/2020 -  Construction & Remodel of Campus Center/ABC Building 
  • 11/2019 – 12/2021- Construction of S&E building

2020

  • 5/2020 – 12/2022- Construction of Gym/Athletics Facilities 
  • 9/2020 – 7/2022- Construction of Arvin program 
  • 11/2020 – 8/2021- Construction of Campus Center Annex
  • 11/2020 – 11/2021- Construction of new driveway on Panorama

2021

  • 3/2021 – 9/2022- Constructions of Delano Learning Resource Center
  • 4/2021 – 3/2022- Construction of Welcome Center
  • 12/2021 – 1/2024- Construction of Agriculture Building

2022

  • 1/2022 – 3/2023- Construction of CSS
  • 4/2022 – 11/2023- Construction of Shafter program

2031

  • 12/2031 – 8/2033- Construction of Public Safety building 

2032

  • 3/2032 – 6/2033- Construction of Humanities Building

2034

  • 3/2034 – 10/2035- Construction of Fine Arts Building

2036

  • 3/2036 – 10/2037- Construction of Language Arts Building 