Measure J Project Schedule as of September 30, 2018

*Please note that as construction continues to evolve on campus, project timelines are subject to change.

2018

  • 8/18 – 2/19 - Upgrades to wireless Technology on Campus 
  • 9/4/18 – 10/19/18 - P8 (student parking lot on University)
  • 10/5/18 – 10/12/18 – P9 (staff parking lot next to tennis courts), P11 (staff parking lot next to LA), Entrance from University closed for renovation
  • 11/18 – 11/19 - Construction of Veterans Resource Center
  • 11/18 - 11/20 -  Construction & Remodel of Campus Center/ABC Building
  • 12/18 – Shut down of Kitchen Begins, moved to Huddle 

 

2019

  • 1/19 Mt. Vernon and Huddle are operational
  • 3/19 –8/19- Construction of Memorial Stadium 
  • 12/19 – 1/22- Construction of S&E building

 

2020

  • 5/20 – 12/22- Construction of Gym/Athletics Facilities 
  • 9/20 – 6/22- Construction of Arvin program 
  • 11/20 – 8/21- Construction of Campus Center Annex
  • 11/20 – 11/21- Construction of new driveway on Panorama

 

2021

  • 3/21 – 11/22- Constructions of Delano Learning Resource Center
  • 4/21 – 2/22- Construction of Welcome Center
  • 12/21 – 1/24- Construction of Agriculture Building


2022

  • 1/22 – 3/23- Construction of CSS
  • 4/22 – 11/23- Construction of Shafter program

 

2031

  • 12/31 – 8/33- Construction of Public Safety building 

 

2032

  • 3/32 – 6/33- Construction of Humanities Building

 

2034

  • 3/34 – 10/35- Construction of Fine Arts Building

 

2036

  • 3/36 – 10/37- Construction of Language Arts Building 

 