Measure J Project Schedules Updated 1/21/21
Program Value: $2 Million
Two Separate Phases:
Phase 1 Complete
Phase 2
Construction Dates: TBD
Current Phase: In Design
Description: Updating all external/green spaces with wireless access points
Contractor: TBD
Construction Dates: May 2019 – April 2021
Building A (Main Building): Anticipated Completion in April 2021
Building B (Kitchen/Cafeteria): Anticipated Completion in April 2021
Current Phase: Construction
Status: On Schedule
Description: New building to house Food Services, Administration, Bakersfield College Foundation, Student Government, and provide a new conference center with flexible room arrangements
Program Value: $43.5 Million
Demolition Company: Interior Demolition, Inc. (IDI)
Contractor: S.C. Anderson
Architect: Ordiz-Melby Architects
Program Value: $18.5 Million
Two separate Phases:
Phase 1 (Track and Field) Complete
Phase 2 (Stands, Press Box, PA System, Scoreboard): In Progress
Construction Dates: February 2020 – February 2021
Current Phase: Construction
Description: Renovations to restrooms, concession stands, and press box. Also, replacement of score board, PA system and field lighting.
Contractor: OHNO Construction (Phase 1)
Colombo Construction (Phase 2)
Architect: Klassen Corporation
Construction Dates: December 2019 – November 2021
Current Phase: Construction
Description: New three-story Science and Engineering building to house offices, labs, and classrooms for the Science and Engineering department
Program Value: $65 Million
Contractor: Bernards
Architect: HMC Architects
Construction Dates: July 2020 - March 2023
Current Phase: In Construction
Description: Building a new gym and field house on the BC campus which will house a gymnasium, office spaces, classrooms, weight room, a field house, locker rooms, training rooms, and a fitness center.
Program Value: $63 Million
Contractor: S.C. Anderson, Inc.
Architect: Cannon
Construction Dates:
Current Phase: Civil Package Construction
Description : Building a new Bakersfield College satellite campus in the Arvin community. This will be a multi-use building with classrooms, offices and other services as needed.
Program Value: $21.5 Million
Contractor (Demolition): Upland Construction
Architect: TBD
Construction Dates: Over the course of Measure J projects
Description: To improve the aging Bakersfield College campus, monies have been set aside for repairs/renovations. These repairs/renovations have been broken up into nine (9) smaller projects.
Program Value: $15 Million
Completed projects:
Projects to Come:
Construction Dates: Over the course of Measure J projects
Various phases, but to date have completed projects at:
Description: Temporary classroom and office space for programs to use as they are moved for Measure J projects
Program Value: $12.2 Million
Next swing space phase will include: Temporary locker rooms for athletics and physical education
Contractor: Various
Architect: AP Architects
Construction Dates: January 2021 - May 2022
Current Phase: Design
Description: Renovation of the current bookstore and business services building to house College Safety, the Health Center, Marketing, Human Resources, Institutional Research and Financial & Administrative Services
Program Value: $8 million
Contractor: TBD
Architect: Ordiz Melby Architects
Construction Dates: February 2021 – May 2022
Current Phase: Pre-Construction
Description: Renovation of the current Administration Building to consolidate departments serving incoming student needs and act as a “one-stop shop”
Program Value: $8 million
Contractor: TBD
Architect: TETER Architects & Engineers
Construction Dates: October 2021 - April 2024
Current Phase: Design
Description: Create an “Agricultural Quad” to house a single-story general agriculture building, greenhouses, a horticulture shop, and a mechanized agriculture show (ag mech).
Program Value: $20million
Contractor: TBD
Architect: TETER Architects & Engineers
Construction Dates: May 2021 - May 2023
Current Phase: Design
Description: Create a Learning Resource Center on the Delano-Timmons campus to house new classrooms, a library and offices, along with new landscaping.
Program Value: $27.9million
Contractor: TBD
Architect: Klassen
Construction Dates: TBD
Current Phase: Programming
Program Value: $27.9million
Contractor: TBD
Architect: TBD
Construction Dates: April 2018 - October 2018
Current Phase: Complete
Description:Renovation to all current BC parking lots
Program Value: $3.6million
Contractor: Central Valley Asphalt
Program Value: $2 Million
Phase 1
Construction Dates: August 2018-March 2019 (Night Work)
Current Phase: Complete
Description: Updating all interior buildings with wireless access points
Contractor: Gold Coast Electric
Program Value: $18.5 Million
Phase 1 COMPLETE
Construction Dates: April 2019-September 2019
Current Phase: Complete
Description: Artificial turf and track replacement
Contractor: Ohno Construction Co.
Architect: Klassen Corporation
Construction Dates: November 2018 – November 2019
Current Phase: In Construction
Status: Slippage to December from November
Description: Improving study area, computer labs, counseling, lounge and other services for student veterans
Program Value: $7 Million
Contractor: JTS Construction
Architect: IBI Architect
Construction Dates: July 2020 - October 2020
Current Phase: Construction
Description: Installing monument signage on the four corners of Bakersfield College: Haley & University, University & Mount Vernon, Mount Vernon & Panorama. Currently have one monument at Haley and Panorama
Program Value: $213,000
Contractor: Upland Construction
Architect: AP Architects